At Platinum Development, or focus is the homeowner and to make the process of
building your new home enjoyable and easy to understand. In this section, you
will find a step by step guide of the building process and an estimated time
frame. Please keep in mind that every project is unique and therefore the time
frame is an estimate that can vary based on the size of the home as well as
other factors.
We take seriously our job of managing every step of the home building process.
Therefore our clients are updated weekly on the completion and progress of every
building step. We also understand that the success and experience of our
clients is directly linked to the amount of customer referrals and repeat
business we experience.
Planning Stage (30-180 days)
Lot selection
Architectural design/planning
Engineering approval
Permit
Scheduling
Site Work (5-7 days)
Lot staked
Excavation
Dirt work
Foundation (15-20 days)
Footings and foundation walls poured
Waterproofing
Backfill
Rough
plumbing installed basement
Garage floors poured
Framing (25-30 days)
Exterior and interior walls framed
Exterior siding and masonry walls
installed
Framing inspection
Roof shingled
Mechanical (10-15 days)
HVAC
Audio
Plumbing
Electrical
Customer review before sheetrock
Pre-Finish
(15-20 days)
Insulation
Sheetrock
Finish
(30-40 days)
cabinets installed
Trim constructed
Hardwood flooring
Tile/stone
Painting
Final Finish
(15-25 days)
Plumbing and light fixtures installed
HVAC and audio completed
Wall
coverings
Appliances installed
Carpet completed
Home is cleaned
Completion
(5-10 days)
Yard final grade
Irrigation and landscaping installed
Final inspections
Closing
MOVE IN!!!
30 Day Customer Service
Minor touch ups, repairs, and adjustments
1 year customer service
Minor touch ups, repairs, and adjustments
5-7 years