  At Platinum Development, or focus is the homeowner and to make the process of
building your new home enjoyable and easy to understand. In this section, you
will find a step by step guide of the building process and an estimated time
frame.  Please keep in mind that every project is unique and therefore the time
frame is an estimate that can vary based on the size of the home as well as
other factors.

We take seriously our job of managing every step of the home building process. 
Therefore our clients are updated weekly on the completion and progress of every
building step.  We also understand that the success and experience of our
clients is directly linked to the amount of customer referrals and repeat
business we experience.

Planning Stage (30-180 days)

Lot selection
Architectural design/planning
Engineering approval
Permit
Scheduling

Site Work (5-7 days)

Lot staked
Excavation
Dirt work

Foundation (15-20 days)

Footings and foundation walls poured
Waterproofing
Backfill
Rough plumbing installed basement
Garage floors poured

Framing (25-30 days)

Exterior and interior walls framed
Exterior siding and masonry walls installed
Framing inspection
Roof shingled

Mechanical (10-15 days)

HVAC
Audio
Plumbing
Electrical
Customer review before sheetrock

Pre-Finish (15-20 days)

Insulation
Sheetrock

Finish (30-40 days)

cabinets installed
Trim constructed
Hardwood flooring
Tile/stone
Painting

Final Finish (15-25 days)

Plumbing and light fixtures installed
HVAC and audio completed
Wall coverings
Appliances installed
Carpet completed
Home is cleaned

Completion (5-10 days)

Yard final grade
Irrigation and landscaping installed
Final inspections
Closing
MOVE IN!!!

30 Day Customer Service

Minor touch ups, repairs, and adjustments

1 year customer service

Minor touch ups, repairs, and adjustments

5-7 years

Start the process of your next Platinum Development Company dream home!